From Sunlight to Site Power: How Turner Construction Company Powered an Off-Grid Trailer [CASE STUDY]


On a clinical drug research facility project in Foster City, Turner’s team turned a temporary power constraint into an opportunity, using solar panels and battery storage to power an off-grid construction trailer instead of trenching conduit across the site or relying on a diesel generator.

The challenge was straightforward: available temporary power was on the far west side of the jobsite, while the trailer setup needed to be on the far east side, roughly a quarter mile away. Rather than spending time and money installing conduit before demolition could begin, the project team worked with Power Shingle to install solar “eyebrows” on a small office trailer. The team decided on a 7.68 kW system paired with two 20kWh batteries. Installed in late 2025, the system powers both the construction and restroom trailers through winter rain and long stretches without sun.

Power Shingle solar array on the eyebrows of Turner’s jobsite construction trailer in Foster City, CA.
Photo courtesy of Nicole Rendon, Turner Construction.

As Regional Sustainability Manager Brett Stuckey put it, “Overall, it’s gone very, very well,” adding that the team “never lost charge in the battery” and hasn’t needed to use any alternate fuel for trailer needs to date.

The benefits were immediate: reduced fuel use, avoided generator rental costs, less site disruption, and dependable power where the team needed it most. Stuckey credited Power Shingle for its availability and coordination but emphasized that this was not a sustainability initiative pushed from the sidelines. “This is a special instance where the project team, the MEP manager, and the procurement agent took the reins and said, ‘we’re going to figure this out.’”

The system proved more resilient than expected

Even during cloudy weather, the panels continued generating power with the batteries, never dropping below a 35% charge even with space heater usage throughout winter. The team even began charging an electric forklift from the same battery system, proving that the setup could support more than basic trailer operations. Stuckey noted that overall costs were lower than renting and fueling a generator.

There were challenges

Stuckey made it clear that teams should not treat PV as a plug-and-play solution without advance planning. Union signatory firms should ensure that union electricians are contracted to install the PVs and batteries. A major consideration is trailer efficiency, with older, less-efficient heating and cooling systems drawing more power than what PV alone can provide. Consider heat pumps at the point of trailer rental. The battery itself is critical: “If we didn’t have the batteries, it wouldn’t have worked,” Stuckey said, noting that crews often start before sunrise and finish after sunset. His main advice is simple. “Do the math.” Compare temporary power, generator power, and PV with battery back-up, including installation needs, fuel, rental costs, carbon, and the total cost of ownership over the project duration.

Considerations for future projects

Setup should begin during logistics planning. Identify trailer locations, available power sources (e.g. solar), the distance to temporary power, expected loads, and any 24-hour power needs before finalizing the trailer power strategy. Then, engage vendors early to size the panel and battery system, confirm trailer compatibility, and plan any electrical labor. Stuckey said teams should look beyond trailers and consider where PV can provide power, such as solar lunch tents that provide shade while charging tools, scissor lifts, electric equipment, or even supporting temporary welding power.

The Foster City installation demonstrates that this approach is feasible when site conditions are right, especially on projects where diesel generators would otherwise provide steady power. “It was fun to be a first for our company,” Stuckey said. If the economics continue to pencil out, it likely won’t be the last.

Posted 10/15/06

About the Author

Emi LaFountain is a Sustainability Manager at Turner Construction, focused on standardizing sustainability programs along the West Coast and identifying and implementing policies and standards aimed towards meeting Turner’s ESG goals. Aside from having worked in construction operations, finance, and procurement roles, and she has also held corporate positions as Turner’s Embodied Carbon Program Manager and Jobsite Carbon Program Manager, where she worked to define the contractor’s role in sustainability and operationalize best practices. Emi was a founding member of the Bay Area Sustainable Construction Leaders group and is an active member of the AGC-California Advocacy Group. She holds an undergraduate degree in environmental engineering from Rice University and has a master’s in Sustainability Leadership from the University of Cambridge.

Related News

Stay connected.

Find out first about industry news, upcoming events + trainings, and updates by signing up for our newsletter. Sign Up!